A multi-section steel deck assembly engineered for a hydroelectric dam walkway replacement — fabrication-ready, site-specific.

Dam project photo 1 Dam project photo 2 Dam project photo 3
Modeled Full deck modeled & detailed in SolidWorks
Fab-Ready Package delivered with full BOM & mfg. drawings
Installed Signed off for structural upgrade at dam site
Overview
  • Multi-section steel deck assembly designed for a hydroelectric dam walkway replacement
  • Engineering drawings interpreted and measurements adjusted to match site-specific constraints
  • 4 independent frame subassemblies modeled, each with unique anchor alignments and bracing geometry
Engineering
  • All frame sections designed in SolidWorks — structural bracing, fastener points, and anchor alignments fully resolved
  • Full bill of materials generated with hardware sourced to spec
  • Detailed manufacturing drawings created to minimize field fit-up time and installation errors
  • Assembly validated across all 4 sections before package handoff
Outcome
  • Fabrication-ready package delivered — reduced field fit-up time and installation errors
  • Structural upgrades at the dam site successfully supported with engineered steel framing
  • Zero design revisions required post-fabrication — drawings matched site dimensions on installation